Current Phase:
Exterior Closure
Office Tower: 55%
Hotel Tower: 75%
Podium: 100%
Foundation: 100%
3 Weeks Look Ahead

October 30th:

  • Complete stone and pavers in the South Tower Level 6 & 7's Decks
  • Install glaze
  • Complete terrazzo flooring in Atrium

November 6th:

  • Complete wall and floor stone installation on Level 6
  • Level 6 Kitchen Sign Off
  • Install Plaza stone

November 13th:

  • Complete installation of metal panels on west elevation
  • Finish wall tile & epoxy flooring on Level 7 pool deck

Construction is underway on the 23-story hotel tower and adjacent 18-story office tower, built over top a single story underground parking garage. Construction required digging the existing surface parking lot to about 14 feet below for the underground garage and foundation structure. The foundation now in place consists of 554 piles extending 25 to 65 feet below.

This exciting development project is intended to increase connectivity between both stadiums, the Downtown Business District, Pioneer Square, Waterfront Park, International District, King Street Station and the hotel conference center.