Current Phase:
Exterior Closure
Office Tower: 55%
Hotel Tower: 75%
Podium: 100%
Foundation: 100%
3 Weeks Look Ahead

October 30th:

  • Complete stone and pavers in the South Tower Level 6 & 7's Decks
  • Install glaze
  • Complete terrazzo flooring in Atrium

November 6th:

  • Complete wall and floor stone installation on Level 6
  • Level 6 Kitchen Sign Off
  • Install Plaza stone

November 13th:

  • Complete installation of metal panels on west elevation
  • Finish wall tile & epoxy flooring on Level 7 pool deck
 