wireframe
crane
Current Phase:
Exterior Closure
Office Tower: 55%
Hotel Tower: 75%
Podium: 100%
Foundation: 100%
3 Week View

Week of July 3rd 2017

GWB: Public Spaces, S07 and N23
Paint:  N23
Casework:  N20
Carpet:  N19
S.Tower Curtainwall:  E11

Week  of July 10th, 2017

GWB:  Public Spaces, S07 and N23
Paint:  N23
Casework:  N21
Carpet:  N20
S.Tower Curtainwall:  E11
Sitework:   King St Right of Way

 Week  of July 17th, 2017

GWB:  Public Spaces, S08, and N23
Paint:  N23
Casework:  N22
Carpet:  N22
S.Tower Curtainwall:  E14
Sitework:  Weller Street Phase IV, King St Right of Way

 

 

 
 
 

Contact Us

Please complete the form below: