Current Phase:
Exterior Closure
Office Tower: 55%
Hotel Tower: 75%
Podium: 100%
Foundation: 100%
3 Week View

Week of May 29th, 2017

GWB: Public Spaces and S06
Paint:  N22
Casework:  N19
Carpet:  N17
S.Tower Curtainwall:  S18

Week  of June 5th, 2017

GWB:  Public Spaces and S07
Paint:  N23
Casework:  N20
Carpet:  N19
S.Tower Curtainwall:  S18

 Week  of June 12th, 2017

GWB:  Public Spaces, S07, and N23
Paint:  N23
Casework:  N20
Carpet:  N19
S.Tower Curtainwall:  E11
Sitework:   King St Right of Way

 

 

 
 
 

Frequently Asked Questions

Q. When will pile driving be done?

A. Steel pile projected to be complete in late Feb; Grout piles to start early March and finish in mid-April

Q. Will I still have access to King Street Station and the Weller Street Pedestrian Bridge?

A. Yes, alternate routes may be needed but there will always be access to the station and bridge.

Q. Can I receive regular notifications?

A. This website has current and pertinent information regarding this project.